All battens are to be check with spacing no more than 600mm,and runs continuous from top to bottom, if the batten toward the joist and bearer is not level, it may be require be packing out or planning down. Head flashing will need to be installed to all joineries using flexible flashing tape (Aluband) to tape it against the top of joinery and building warp, then lapping vent strip over the head flashing and tape against the building wrap as well. Both side of the head flashing will be fitted with stopper with sealant.

Sunday, April 24, 2011


Fix nogs between framing to create a space for power box to fix to. Creat moisture resistant opening as window and seal with flashing on top and side of the power box. Alue Band tap head flashing and vent strap on top of the power box and fix extra cavity batten around for weatherboard.


To adjust exterior door and window, measure equal and same distant from top plate to top of the exterior joineries, level horziontal on top and minimum 10mm protude out the framing at inside of the house for Gib then tag window.

pack bottom/top and two side for level and straighten joinery frame center as possible and then nail off with jog head nail and punch in.



cavity batten of 20mm thick and 40-60mm wide fixed max of 600mm spacing on to the exterior of timber framing over the building wrap. Horizontal batten on top of the wall framing should be continuous with no gaps, vertical batten to all interior/exterior corners and both side of the window/door should be thin down for difference of lashing and easier to slide cladding behind the joineries. horizontal battens under window and doors should be fixed in a 5 degree angle with minimum of 50mm gape to the vertical batten allow water to run out.
Vent strip is to be fix alone the bottom of the batten about the height of the bearer, batten is to be taken a bit off in order to slid into the vent strip. 50mm PVC corner flashing are to be fixed to all internal and external corners running continuously or over lapping top to bottom, use same flashing for both internal and external as the lip folds both ways
At window and door opening, cut warp and fold into the house, use window sealant tape (Alue Band) to tape continuous on the bottom of opening with a up fold of 200mm on the end, 200mm taping on each of the top corner and taping over the cuts again on all corners














Building wrap is to be wrap around the building from bearer upward in full length of the wrap, wrapping top over the bottom sheet if more covering is required, minimum 150mm is required for all lapping

Blue ribbon tape is then fix around the house in between the space of the nogs stopping building wrap blow against the exterior cladding.


















After roof cladding, gutter and fascia. Builder can fit soffit
board onto the eve of the roof


Boxed soffit was form when building timber roof framing. Soffit board is then cut in size and slide in between the fascia and nail onto the boxing. Nail hole must be pre-drill and nail with a special plastic made plug for fixing and looks. Joints of the soffit board will be fitted with a plastic strip covering the joints and moulding will be use to cover the cut joints between the wall cladding and the soffit.